― ERA PREMIER CUSTOM HOME BUILDING COST

Custom home building cost in Toronto: the real 2026 numbers.

What builders actually charge per square foot, what the City and York Region add on top, and the site-specific and tax costs most cost guides leave out entirely.

GUIDE, NOT A QUOTE

Every number here is a range, not a quote.

Every range below states its date and exactly what it does and does not include. Land, government charges, site-specific costs and taxes are called out separately, never folded into one number.

Method

Published rates from GTA custom home builders

Date

Published September 2026

Source

City of Toronto, City of Markham, City of Richmond Hill, CRA and StatCan, plus 9 GTA builders

Review

Reviewed by ERA Premier’s project team

― READING THIS NUMBER CORRECTLY

Compare the basis before the number.

A cost range only means something once you know what it measures. Here is exactly what is in ours, checked against the same six things worth checking on anyone else’s.

Area basis

What is being measured?

Construction only, measured on interior conditioned floor area. Lot size and site area are not part of the $/sqft figure.

Scope basis

Hard and soft costs

Our $/sqft ranges are hard construction costs only. Soft costs (design, engineering, survey) run 5 to 15% of that budget on top, see the drivers section below.

Project condition

Site or existing house

A teardown-rebuild carries demolition, and on tight infill lots, shoring and utility reconnection. A vacant or serviced lot often does not. See the site-specific section below for typical figures.

Specification

Finish and system level

Standard, mid-range and luxury tiers below are defined by finish, cabinetry, fixtures and mechanical systems, not by square footage.

Allowances

Selections and contingency

A 10 to 15% contingency is standard, and any allowance above it is a selection you control, not a hidden cost.

Governance

Date and exclusions

Every figure on this page states its date. Where a reliable number is not available (land cost by neighbourhood, current Development Charges in Mississauga and Oakville), we say so instead of guessing.

― COST PER SQUARE FOOT

What builders actually charge, by tier.

Ranges based on published GTA sources, September 2026. These cover construction cost only; everything else on this page is listed separately.

Finish tier
Blended range
Full market spread

Standard / entry

$350–$470/sqft

$250–$550/sqft

Mid-range

$450–$580/sqft

$350–$650/sqft

Luxury

$600–$930/sqft

$400–$1,000+/sqft

All-in / turnkey (construction + soft costs)

$450–$700+/sqft

not tracked separately

These are ranges, not a quote

Your finish selections, lot and scope decide where you land within these ranges. The single biggest swing factor is finish level, cabinetry, millwork, flooring, fixtures and mechanical systems can run 2.5 to 3 times higher per square foot at the luxury end than the standard end.

― EXAMPLE COST BY HOME SIZE

What that looks like at 2,500 and 3,000 square feet.

Illustrative calculations only, the blended per-square-foot ranges above multiplied by two common home sizes. Land, government charges, site-specific costs and soft costs all sit on top of these figures.

Finish tier
2,500 sqft
3,000 sqft

Standard / entry

$875,000–$1,175,000

$1,050,000–$1,410,000

Mid-range

$1,125,000–$1,450,000

$1,350,000–$1,740,000

Luxury

$1,500,000–$2,325,000

$1,800,000–$2,790,000

All-in / turnkey

$1,125,000–$1,750,000+

$1,350,000–$2,100,000+

Illustrative math, not a quote

Everything in the sections below, government charges, site conditions and the tax rebate, sits alongside these figures. It does not net out against them.

― WHAT THE CITY ADDS ON TOP

The part most cost guides don’t show you.

Before a single stud goes up, building in Toronto carries real, published municipal charges, and they are worth budgeting for from day one.

Development Charges. For a single or semi-detached home, the City of Toronto’s Development Charge is $137,846 per unit (June 2024 rate, with a Section 27 agreement in place) or $143,409 per unit (May 2025 indexed rate, without one). Indexing is frozen through 2025 and 2026 under a City Council decision (MM29.16). On a 2,500 to 3,000 square foot home, that works out to roughly $46 to $57 per square foot added before construction even starts. The May 2025 charge breaks down as Transit 38.5%, Roads 21.2%, Water/Sewer/Storm 15.3%, Parks and Recreation 14.7%, with the remainder across smaller categories.

Building permit fee. $18.56 per square metre (about $1.72 per square foot), with a $214.79 minimum, effective January 1, 2026.

HST. A flat 13%, applying to most construction labour and materials, though see the tax section below for a real rebate that can offset part of this.

One industry estimate, citing CMHC data, puts the total government charges on a new Toronto detached home (Development Charges plus education-related charges and parkland contributions) at approximately $180,600, or roughly 9% of the home’s price, a broader figure than Development Charges alone. CMHC’s own research also shows that Toronto and Vancouver carry the highest government charges of any major Canadian market, over 20% of build cost in the most expensive cases.

― DOES THE CITY OR REGION CHANGE WHAT YOU PAY?

Building outside Toronto proper: what actually changes.

Yes, and it is real money, not a rounding error. Development Charges are set independently by each municipality, plus York Region and local school boards where applicable. We pulled each city’s own current, published rate schedule for a single or semi-detached home rather than estimate this.

Municipality
Development Charges, single/semi-detached (per unit)
Source dates

Toronto

$137,846–$143,409

City of Toronto, June 2024 (with Section 27 agreement) to May 2025 (indexed)

Richmond Hill

$144,428 ($50,776 city + $84,718 York Region + $8,934 school boards)

City of Richmond Hill, city and education rates as of July 2026, York Region as of May 2026

Markham

$179,391 ($78,007 city + $92,834 York Region + $8,550 school boards)

City of Markham, rates as at January 2026

Two honest gaps

Mississauga is partway through a 50% development charge reduction program (in effect since January 2025), and Oakville’s Development Charges by-law is currently under review with a new one expected in 2027, so neither city has a stable current total to publish here. We confirm those figures at the time of your quote.

― WHAT ELSE CHANGES YOUR NUMBER

Site-specific costs, and what actually drives your price per square foot.

Some of these depend on your finish choices. Others depend on your specific lot and address, not on whether you choose standard or luxury finishes.

Finish level

The largest single driver. Cabinetry, flooring, millwork, fixtures and mechanical systems can run 2.5 to 3 times higher per square foot from standard to luxury.

Committee of Adjustment

If your project does not meet zoning as-of-right, common on many infill lots, the City’s minor variance fee is $2,228.98, plus $3,000 to $8,000 for a planning consultant.

Shoring and excavation

On tight infill lots close to a neighbouring foundation, shoring is standard, not optional. Toronto shoring jobs commonly run $8,000 to $50,000.

Utility connections

Connecting hydro, water, drain and gas on a full custom build runs an estimated $25,000 to $40,000-plus, confirm this for your specific address.

Soft costs

Architectural and engineering fees typically run 5 to 15% of the construction budget.

Contingency

A realistic reserve for changes and unforeseen conditions is 10 to 15% of the construction budget.

Demolition and site prep

If an existing structure needs to come down first, that is a separate line item, one illustrative example put a teardown at roughly $100,000 on a 3,000 square foot lot.

Land cost

Land cost varies too much by neighbourhood and lot to publish a reliable range. It needs to be assessed for your specific property.

― THE REBATE ALMOST NOBODY MENTIONS

A real HST rebate, and other fees to plan for.

Ontario’s Enhanced New Housing Rebate. This is a current program that many cost guides do not mention. For an owner-built home where construction starts between April 1, 2026 and March 31, 2027, and is substantially completed before 2030, this rebate, combined with the existing GST/HST New Housing Rebate for owner-built homes, can return up to $80,000 in HST paid on a home valued up to $1,850,000, or the actual provincial HST paid, whichever is less. Eligibility depends on your specific circumstances, including occupying the home as your primary residence, and claiming it requires Form GST191 filed with the CRA. This needs a qualified accountant to confirm and file for your situation, but it is real money on the table, and the construction-start window is open right now.

Tarion enrolment. A Tarion-registered new home carries its own enrolment fee, paid by the builder and typically built into the overall project cost. Ask your builder to show it as a separate line item.

Current Building Code. The 2024 Ontario Building Code, in force since January 1, 2025, includes enhanced energy-efficiency requirements that can affect material and system costs on new builds. Ask your builder how their pricing already accounts for current code requirements.

― WHERE THE MARKET IS RIGHT NOW

2026 pricing context.

Statistics Canada’s Building Construction Price Index shows Toronto residential construction costs down 0.8% quarter-over-quarter in Q2 2026, one of only three major Canadian markets to decline that quarter, against a national composite that rose 0.5% quarter-over-quarter and 2.3% year-over-year. Separately, the Altus Group 2026 Cost Guide (released April 2026) describes construction costs in Toronto as stabilizing to softening through 2025 and 2026. Neither changes the ranges above meaningfully, but this is not a market where waiting has historically meant paying more.

― GETTING AN ACCURATE NUMBER

Why we don’t publish a fixed rate card, and what we do instead.

Every range on this page is real, but it is still a range. Your actual number depends on your lot, your finish selections, and whether Committee of Adjustment or shoring applies.

Property and scope review

Start with the address, your goals, and whatever survey or drawings already exist.

Government charges for your address

Toronto, Richmond Hill, Markham or another GTA municipality, confirmed specifically for your lot.

Site conditions

Lot width, proximity to neighbouring foundations, and whether Committee of Adjustment applies.

Finish-level selections

Standard, mid-range or luxury, and where you want to spend versus save.

Real trade and consultant pricing

Once the scope is clear, real quotes replace these ranges.

Your number

A property-specific estimate, not an average.

― HOW TO COMPARE THIS AGAINST ANY QUOTE

Check what is included before comparing.

Use this table as a reading checklist, for our numbers or anyone else’s. A number can look precise while describing a completely different scope.

Cost component
What our number includes
Why it’s separate

Area basis

Construction only, measured on interior conditioned floor area. Lot size and site area are not included.

Different measurement rules can make similar rates describe different quantities of work.

Hard construction

Structure, systems and finishes for the tier you choose, see the tier table above.

A construction-only price leaves out costs you’ll still have to pay.

Design and consultants

Not included in the $/sqft figure. Architectural and engineering fees run 5 to 15% of the construction budget, on top.

The professionals you need depend on the property and the design.

Permits and fees

Not included. Development Charges, the building permit fee and, where applicable, Committee of Adjustment fees are all separate, see the sections above.

Fees and requirements depend on your project and your city.

Taxes

Not included. HST is a flat 13%, though a real rebate can offset part of it for an owner-built home, see the tax section above.

Make sure both numbers include tax, or neither does.

Site / existing conditions

Not included. Demolition, shoring and utility connections are real, site-dependent costs, see the site-specific section above.

Tight sites and unknown conditions can add work a general price doesn’t cover.

Finishes and allowances

Defined by the tier tables above, standard, mid-range or luxury.

“Mid-range” can mean very different things, so look at the actual materials and fixtures.

Contingency

Not included in the base range. Budget 10 to 15% of the construction cost on top.

Contingency treatment changes how complete or resilient the budget appears.

Exclusions

Land, government charges, site-specific costs, soft costs, contingency and tax, all stated explicitly above, not folded into one number.

Ask what’s left out, so a partial price doesn’t look like the whole budget.

Publication rule

Any numerical guidance we publish states its source, its preparation date, its area and scope basis, and what it leaves out. That is the standard this page holds itself to.

― CREDENTIALS

Licensed, and building custom homes in the GTA for over a decade.

  • HCRA Licence #48554, licensed, in good standing since October 2020.
  • Tarion-registered builder.
  • Founded 2015 by Ali Kashani, Founder and CEO.
  • 5.0★ on Google (11 reviews, as of September 2026).
― OTHER COST GUIDES

Adding space, or working within your existing home?

This page covers a new custom build. If your project adds space to an existing home, or works within it, one of these fits your project better.

More space

Home Addition Cost

For rear, side or upper-level expansion connected to an existing home.

Best fit when: the project adds new floor area while retaining part of the house.

Existing home

Home Renovation Cost

For coordinated major renovations involving several connected scopes.

Best fit when: the existing home remains but its layout, systems or finishes change substantially.

― CUSTOM HOME BUILDING COST, FAQ

Understand what the number represents.

Typically the structure, systems (electrical, plumbing, HVAC) and finishes that go into the build itself. It does not typically include land, Development Charges, permit fees, Committee of Adjustment or shoring costs where they apply, architectural and engineering soft costs, or selections above a set finish allowance.

No. Land cost varies too much by lot and location to publish a reliable range. Land needs to be priced for your specific property.

Finish level is the single biggest swing factor, luxury-tier finishes, cabinetry and mechanical systems can run 2.5 to 3 times higher per square foot than standard-tier ones. After that, Development Charges are the largest fixed cost most homeowners do not anticipate.

For a single or semi-detached home, City of Toronto Development Charges alone run $137,846 to $143,409 per unit (roughly $46 to $57 per square foot on a 2,500 to 3,000 square foot home), plus a building permit fee of about $18.56 per square metre with a $214.79 minimum, plus 13% HST on most labour and materials.

Development Charges alone create a real difference. Toronto runs $137,846 to $143,409 per unit, Richmond Hill $144,428 per unit, and Markham $179,391 per unit, each set independently by the city, York Region and local school boards. Mississauga and Oakville are both mid-change on their charge structures right now, so we confirm those specifically at the time of your quote.

If your project does not meet zoning as-of-right on setbacks, height or lot coverage, common on many infill lots, the City’s minor variance fee is $2,228.98, plus roughly $3,000 to $8,000 for a planning consultant. Not every project needs one, it depends on your specific lot.

Shoring protects a neighbouring foundation during excavation on tight lots, standard on narrow infill sites close to an adjacent property, and typically unnecessary on wide, standalone suburban lots. Toronto shoring jobs commonly run $8,000 to $50,000.

No. Connecting or reconnecting hydro, water, drain and gas is a separate cost, published estimates from GTA builders range from roughly $25,000 to $40,000 or more on a full custom build. Confirm this for your specific address.

Yes, and it is a real, current program most cost guides do not mention. Ontario’s Enhanced New Housing Rebate, combined with the existing GST/HST New Housing Rebate for owner-built homes, can return up to $80,000 in HST for a home valued up to $1,850,000, if construction starts between April 1, 2026 and March 31, 2027, and is substantially completed before 2030. A qualified accountant needs to confirm your specific eligibility and file Form GST191.

10 to 15% of the construction budget is the commonly cited range for a custom build, on top of the soft costs, government charges and any site-specific costs covered above.

It depends heavily on the existing structure and site access. One illustrative example puts a teardown around $100,000 on a 3,000 square foot lot, but this needs to be assessed for the specific property.

No. Ontario’s HST is a flat 13%, applied on top of most construction labour and materials, though see the rebate question above for a real way to offset part of it.

Recent Statistics Canada data shows Toronto construction costs actually declining slightly quarter-over-quarter, one of only three major Canadian markets to do so, while industry cost guides describe the broader market as stabilizing to softening. It is not a market where waiting has historically added cost.

Get your scope and finish selections locked in before pricing starts, changes made mid-build cost more than the same decision made on paper. Within that, moving between the standard, mid-range and luxury tiers above is the biggest lever you actually control.

A longer timeline generally means longer exposure to financing and holding costs, on top of the construction cost itself, even if the per-square-foot rate does not change. A realistic schedule, confirmed as part of your quote, is worth asking for.

Treat calculators as a rough starting point at best, most are too generic to reflect a specific lot. Start instead with a property and scope review, your lot, finish selections, Development Charge exposure and any site-specific costs all factor into a real number in a way a published range or calculator cannot.